ContactPost: CIVIL AVIATION AUTHORITY OF MALAYSIA Tel: 6-03-8778 4106 Email: ais@caam.gov.my URL: aip.caam.gov.my | AIP Supplement for Malaysia![]() | AIRAC AIP SUP 38/26 Effective Date: 03 SEP 2026 Publication Date: 23 JUL 2026 |
1.1 The Penang International Airport is currently undergoing an upgrade program. This involves the expansion of the main apron, rehabilitation of the existing apron taxiway, introduction of a new helicopter apron and introduction of a new Aircraft Stand Taxilane L, new Helicopter Stand Taxilane M and new Aircraft Stand Taxilane N.
1.2 The following temporary changes concerning Penang Aerodrome (WMKP) is taking place due to upgrading works from 1st March 2025 until 1st July 2027. This project is structured into four distinct phases. A comprehensive breakdown of the activities and current status for each phase is provided in the table below, with Phases 1 and 2 completed.
| Phase | Start Date | Finish Date | |
|---|---|---|---|
| 1 | Phase 3 (Apron Taxiway Rehabilitation Works) | 19th JUL 2026 | 22nd JUN 2027 |
| 2 | Phase 4 (Realignment Apron Taxiway) | 23rd JUN 2027 | 1st JUL 2027 |
1.3 The working areas for the rehabilitation exercise are detailed in the remarks.
APRONS, TAXIWAYS AND CHECK LOCATIONS/POSITIONS DATA
| Apron surface and strength |
Bay 1L, Bay 1, Bay 1R, Bay 2, Bay 3, Bay 5, Bay 8, Bay 11 Surface: Concrete (Rigid) Strength: PCR 1360 / R / D / W / U |
|
Bay 4, Bay 5L, Bay 5R, Bay 6, Bay 7, Bay 8L, Bay 8R Surface: Concrete (Rigid) Strength: PCR 685 / R / C / W / U | |
|
Bay 3R, Bay 9, Bay 10, Bay 11L, Bay 11R Surface: Concrete (Rigid) Strength: PCR 704 / R / D / W / U | |
|
Bay 3L, Bay 2L, Bay 2R Surface: Concrete (Rigid) Strength: PCR 157 / R / D / W / U | |
|
Bay A1, Bay A2, Bay A3, Bay A4, Bay A5, Bay A6 Surface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T | |
|
Bay H1, Bay A7 Surface: Concrete (Rigid) Strength: PCR 160 / R / C / W / T | |
|
Bay 12, Bay 12L, Bay 12R, Bay 13, Bay 14, Bay 15L, Bay 15, Bay 15R, Bay 16, Bay 16R, Bay 17, Bay 18, Bay 19 Surface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T | |
|
Bay C1 Surface: Concrete (Rigid) Strength: PCR 800 / R / C / W / U | |
|
Bay C2 and Bay C3 Surface: Concrete (Rigid) Strength: PCR 715 / R / B / W / U | |
| Taxiway width, surface and strength |
Taxiway A and Taxiway E Width: 23 m Surface: Asphalt (Flexible) Strength: PCR 577 / F / A / W / U |
|
Taxiway A/04 Width: 30 m Surface: Concrete (Rigid) and Asphalt (Flexible) Strength: PCR 787 / R / A / W / U and PCR 577 / F / A / W / U | |
|
Taxiway A/22 Width: 30 m Surface: Asphalt (Flexible) Strength: PCR 577 / F / A / W / U | |
|
Taxiway B Width: 34 m Surface: Concrete (Rigid) and Asphalt (Flexible) Strength: PCR 643 / R / A / W / U and PCR 481 / F / A / W / U | |
|
Taxiway C Width: 23 m Surface: Asphalt (Flexible) Strength: PCR 481 / F / A / W / U | |
|
Taxiway D Width: 34 m Surface: Asphalt (Flexible) Strength: PCR 481 / F / A / W / U | |
|
Taxiway F Width: 31 m Surface: Asphalt (Flexible) Strength: PCR 577 / F / A / W / U | |
|
Taxiway G Width: 32 m Surface: Asphalt (Flexible) Strength: PCR 577 / F / A / W / U | |
|
Taxiway H Width: 42 m Surface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T | |
|
Taxiway J Width: 25 m Surface: Concrete (Rigid) Strength: PCR 715 / R / B / W / U | |
|
Aircraft Stand Taxilane J1 Width: 25 m Surface: Concrete (Rigid) Strength: PCR 715 / R / B / W / U | |
|
Apron Taxiway K Width: 24 m Surface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T | |
|
New Aircraft Stand Taxilane L Width: 24 m Surface: Concrete (Rigid) Strength: PCR 1250 / R / C / W / T | |
|
New Helicopter Stand Taxilane M Width: 13 m Surface: Concrete (Rigid) Strength: PCR 160 / R / C / W / T | |
|
New Aircraft Stand Taxilane N Width: 20 m Surface: Concrete (Rigid) Strength: PCR 160 / R / C / W / T | |
|
Remarks |
PHASE 2 (APRON EXPANSION) Several amendments and changes to the Aircraft Operations Area (AOA) will take place during this phase. The changes and amendments affecting the AOA are listed below in the order shown:
Note: The effective dates of all operational changes associated with Phase 2, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment, as appropriate, in accordance with the AIRAC cycle where applicable |
|
PHASE 3 (APRON TAXIWAY REHABILITATION WORKS) Several amendments and changes to the Aircraft Operations Area (AOA) will take place during this phase. The changes and amendments affecting the AOA are listed below in the order shown:
Note: The effective dates of all operational changes associated with Phase 3, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment, as appropriate, in accordance with the AIRAC cycle where applicable. | |
|
PHASE 4 (REALIGNMENT APRON TAXIWAY) Several amendments and changes to the Aircraft Operations Area (AOA) will take place during this phase. The changes and amendments affecting the AOA are listed below in the order shown.
Note: The effective dates of all operational changes associated with Phase 4, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment, as appropriate, in accordance with the AIRAC cycle where applicable. |
SURFACE MOVEMENT GUIDANCE AND CONTROL SYSTEM AND MARKING
| Remarks |
Note: The effective date for each change and amendment to the Taxiway lights and Visual Docking and Guidance System will be notified from time to time via NOTAM or AIP Amendment, in accordance with the sequence of works. |
AERODROME OBSTACLES
| OBST ID/Designation | OBST Type | OBST Position | ELEV/ HGT | Markings/ Type, Colour | Remarks |
|---|---|---|---|---|---|
| PC-5 | Piling Crane |
051742.61N 1001612.47E | 4 m / 19 m | Marked/LIM R |
Piling machine reach 19 m. Obstacle in position effective from 6th May 2025 till 18th November 2026 EST. |
OTHER LIGHTING, SECONDARY POWER SUPPLY
| 5 |
Remarks |
Taxiway edge and centre line lights not available for:
The effective dates of all operational changes associated with Phase 2, 3 & 4, including the introduction of new facilities and temporary closures, will be promulgated by NOTAM and/or AIP Amendment (AIP AMDT), as appropriate, in accordance with the AIRAC cycle where applicable.
|
1.4 Local traffic regulations (additional)
1.4.1 Taxiing to and from stands
Aircraft movement will not be permitted in closed portions of the apron taxiway, parking bays and taxiways.
The routes to be used by aircraft when taxiing entering or exiting from Apron will be specified by Air Traffic Control. The issuance by Air Traffic Control of a taxi route to an aircraft does not relieve the pilot-in-command of the responsibility to maintain separation with other aircraft on the movement area or to comply with Air Traffic Control directions intended to regulate aircraft movement.
During the construction period, pilots are advised to be cautious of open excavation, workers, construction materials, and equipment, especially when taxiing on the Taxiway and Apron Taxiway near cordoned or barricaded areas where work is ongoing.
2.1.1 Construction on existing Bay B9 and Taxiway H will commence only after the completion of all construction work on the wide-body apron-taxiway areas from Bay A9. These areas will be closed during the construction period.
2.1.2 Construction works will be carried out 24 hours a day in the closed apron expansion area.
2.1.3 Construction works for Taxiway H shoulder outside construction hoarding and apron marking will be carried out during runway closure hours.
2.1.4 The closure of Taxiway H will occur exclusively in this phase
2.1.5 The entire apron expansion works will be completed by 18th July 2026 EST.
2.2.1 Taxiway rehabilitation works will commence from existing Bay B7 to Bay A6L, and then continue from Bay A8 to Bay A7.
2.2.2 The taxiway closures will occur in phases, commencing with the closure of TWY G and subsequently followed by the closure of TWY F. Construction works on the shoulders of TWY F and TWY G outside the construction hoarding will be carried out during runway closure hours.
2.2.3 Apron marking will be carried out during runway closure hours.
2.3.1 All bay lead lines will be connected to the new apron taxiway centre line.
2.3.2 The centre line of the apron taxiway leading to all new aircraft bays will be realigned to match the new apron taxiway centre line.
2.3.3 Apron marking works will be carried out during runway closure hours.
3.1 Refer charts below for additional information:
Apron Taxiway Rehabilitation (Phase 3)
Appendix 1A: Aerodrome / Heliport Chart – ICAO (AD2-WMKP-2-1)
Appendix 1B: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-3)
Appendix 1C: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-4)
Appendix 1D: Aerodrome Ground Movement Chart – ICAO (AD2-WMKP-2-5)
Realignment Apron Taxiway (Phase 4)
Appendix 2A: Aerodrome / Heliport Chart – ICAO (AD2-WMKP-2-1)
Appendix 2B: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-3)
Appendix 2C: Aircraft Parking Docking Chart – ICAO (AD2-WMKP-2-4)
Appendix 2D: Aerodrome Ground Movement Chart – ICAO (AD2-WMKP-2-5)
4.1 Any information and queries to contact:
| Name | : | Mohd Ridzuan bin Ahmad Walid |
| Designated | : | Head of Operations, MASB Penang International Airport |
| : | ridzuanaw@malaysiaairports.com.my |
5.1 This AIRAC AIP Supplement supersedes AIRAC AIP SUP 32/26 and will remain in force until the works complete on 1st July 2027 EST. Any updates, changes or cancellation of this AIRAC AIP Supplement will be notified through NOTAM.
5 - END -