ContactPost: CIVIL AVIATION AUTHORITY OF MALAYSIA Tel: 6-03-8529 1318 Fax: 6-03-8529 1310 AFS: WMKKYAYS Email: ais@caam.gov.my URL: aip.caam.gov.my | AIP Supplement for Malaysia![]() | AIRAC AIP SUP 32/25 Effective Date: 10 JUL 2025 Publication Date: 05 JUN 2025 |
1.1 The following temporary changes concerning Kota Bharu Aerodrome (WMKC) is taking place due to upgrading works from 30th April 2024 until 30th June 2026 EST. Upgrading works will be divided into 2 Phases. Phase 2A will take place from 30th April 2024 until 29th May 2025 EST. Phase 2B will take place from 30th April 2024 until 30th June 2026 EST.
1.2 During Phase 2, new Bay 6, Bay 7, Bay 8, Bay 9, Bay 10 and Bay 11/Bay 11A have been activated as permanent aircraft stands. Bay 1, Bay 2, Bay 3, Bay 4 and Bay 5 are closed for upgrading works.
1.3 For Phase 2A, new Taxiway A and Taxiway C have been activated as permanent taxiways.
1.4 During Phase 2B, Taxiway B, Taxiway B1, Taxiway E (between Taxiway B to Taxiway C) and Taxiway E (between Taxiway A to Taxiway L) closed for upgrading works. Details of the taxiway closure will be mentioned in the remarks.
1.4.1 WMKC AD 2.8 APRONS, TAXIWAYS AND CHECK LOCATION/POSITIONS DATA
1 |
Apron surface and strength | BAY 6, BAY 7, BAY 8, BAY 9, BAY 10, BAY 11 and BAY 11ASurface: Concrete (Rigid) Strength: PCR 660 / R / B / W / T |
2 |
Taxiway width, surface and strength |
TWY A Width: 25 M Surface: Asphalt (Flexible) Strength: PCR 651 / F / D / X / U |
TWY A1 Width: 18 M Surface: Asphalt (Flexible) Strength: PCR 651 / F / D / X / U | ||
TWY B Width: 26 M Surface: Asphalt (Flexible) Strength: PCR 651 / F / D / X / U | ||
TWY C Width: 18 M Surface: Asphalt (Flexible) Strength: PCR 527 / F / B / X / T | ||
TWY D Width: 17 M Surface: Asphalt (Flexible) Strength: PCR 651 / F / D / X / U |
TWY E Width: 18 M Surface: Asphalt (Flexible) Strength: PCR 651 / F / D / X / U | ||
TWY E (EXT.) Width: 18 M Surface: Asphalt (Flexible) Strength: PCR 650 / F / B / X / T | ||
TWY F Width: 14 M Surface: Asphalt (Flexible) Strength: 8.3 Tonnes | ||
TWY G Width: 21 M Surface: Asphalt (Flexible) Strength: PCR 507 / F / D / X / U | ||
TWY H Width: 13 M Surface: Asphalt (Flexible) Strength: 8.3 Tonnes | ||
TWY L & L1 Width: 18 M Surface: Asphalt (Flexible) Strength: PCR 650 / F / B / X / T | ||
APRON TAXIWAY J Width: 18 M Surface: Concrete (Rigid) Strength: PCR 660 / R / B / W / T | ||
5 | Remarks |
PHASE 2A
PHASE 2B
|
1.4.2 WMKC AD 2.9 SURFACE MOVEMENT GUIDANCE AND CONTROL SYSTEM AND MARKINGS
4 | Remarks | TWY Centre Line LGT TWY C U/S FM 20250530 TIL 20250901 ESTNew visual docking and guidance system for Bay 6, 7 & 8 FM 20240430 TIL PERM |
1.4.3 WMKC AD 2.10 AERODOME OBSTACLES (ADDITIONAL)
In Area 3 | |||||
---|---|---|---|---|---|
OBST ID/Designation | OBST type | OBST position | ELEV/HGT | Markings/Type, colour | Remarks |
a | b | c | d | e | f |
TC-4 | Tower crane | 061011.4N 1021732.6E | 5 m / 45 m | Marked / LIM R |
Crane jib reach 66 m Obstacle in position FM 20240116 TIL20250824 EST |
TC-5 | Tower crane | 061012.1N 1021736.6E | 5 m / 38 m | Marked / LIL R |
Crane jib reach 65 m Obstacle in position FM 20240116 TIL20250824 EST |
TC-6 | Tower crane | 061010.5N 1021734.6E | 5 m / 36 m | Marked / LIL R |
Crane jib reach 56 m Obstacle in position FM 20240116 TIL20250824 EST |
TC-7 | Tower crane | 061008.2N 1021739.7E | 5 m / 36 m | Marked / LIL R |
Crane jib reach 50 m Obstacle in position FM 20240116 TIL20250824 EST |
1.4.4 WMKC AD 2.15 OTHER LIGHTING, SECONDARY POWER SUPPLY
3 | TWY edge and centre line lighting |
PHASE 2A
PHASE 2B
|
1.4.5 WMKC AD 2.20 LOCAL TRAFIC REGULATIONS (ADDITIONAL)
Taxiing to and from stands:
No aircraft movement is allowed at closed portions of apron taxiway, aircraft stand taxi lane, parking bays and taxiways.
The routes to be used by aircraft when taxiing into, on and out of the apron will be specified by ATC. The issuance of a taxi route by ATC does not relieve the pilot-in-command of the responsibility to maintain separation with other aircraft in the movement area or to comply with ATC directions intended to regulate aircraft movement.
Pilots are advised to take note of the precautions on the presence of open excavation, workers, construction materials and construction equipment, particularly when taxiing adjacent to the apron and aircraft bays/stand while works within the cordoned/barricaded areas are in progress.
During Phase 2, new Bay 6 and Bay 7 shall operate for A20N/A21N, B38M/ B738/ B739/E290 aircraft. New Bay 8 shall operate for A20N/A21N, B38M/ B738/ B739. New Bay 9 shall operate for A20N/A21N, B38M/B738/B739, AT75/AT76 and E290 aircraft. New Bay 10 and Bay 11 shall operate for AT75/AT76 aircraft. All bays shall be Power-In Push-Back operation. Bay 11A shall operate for B738/B739 and Power-In Power-Out operation.
1.5 Refer appendices for additional information:
APPENDIX A: Aerodrome/Heliport Chart-ICAO (Phase 2A)
APPENDIX B: Aircraft Parking/Docking Chart-ICAO (Phase 2A)
APPENDIX C: Aerodrome Ground Movement Chart-ICAO (Phase 2A)
APPENDIX D: Aerodrome/Heliport Chart-ICAO (Phase 2B)
APPENDIX E: Aircraft Parking/Docking Chart-ICAO (Phase 2B)
APPENDIX F: Aerodrome Ground Movement Chart-ICAO (Phase 2B)
2.1 Any information and queries to contact:
Name: Mr. Mohammad Faris Norazman
Designated: Head of Operation, MASB Kota Bharu
Email: farisnorazman@malaysiaairports.com.my
3.1 This AIRAC AIP Supplement will remain in force until 30th June 2026 EST. Any updates, changes and cancellation to this AIRAC AIP Supplement will be notified through NOTAM.