AIC for Malaysia

AIC

01/2023

Effective from 14 MAR 2023

to UFN

Published on 14 MAR 2023

  KUCHING INTERNATIONAL AIRPORT (WBGG)
PROPOSED NEW ROYAL MALAYSIA POLICE AIR OPERATIONS FORCE BASE, SARAWAK

1  INTRODUCTION

1.1 This Aeronautical Information Circular serves as notice regarding the works for the construction of New Royal Malaysia Police Air Operations Force Base at Kuching International Airport, Sarawak.
1.2 The duration of overall construction is Forty-Two (42) months from 15 December 2021 and is expected to complete by 14 June 2025, of which this new Royal Malaysia Police Air Operations Force Base will replace the old base.
1.3 This AIC will be followed by an AlP Supplement that will provide the details of the New Royal Malaysia Police Air Operations Force Base with operational details and facilities.

2  SCOPE OF WORKS

2.1 The scope of works prescribed for the above exercise are as follows: -
  1. Soil investigation, earthwork and drainage works.

  2. New Parking Apron on elevated platform to accommodate one (1) Code B aircraft stand with power-in/power out operations and one (1) helicopter stand.

  3. New Exit Taxiway for Code B aircraft operations with 10.5 m wide on ground and elevated platform to connect the new parking apron to the existing runway.

  4. New Aeronautical Ground Lighting (AGL) installation and High Mast.

  5. New Hangar.

  6. New Administration Building.

  7. New Storm Shelter.

  8. New Engine Ground Run and Wash Bay.

  9. New Multi Purpose Hall.

  10. New Guard House.

  11. New Road and Car Park facilities.

  12. Airside and Landside Drainage.

  13. Other Ancillary Buildings.

3  PHASINGS AND WORK PROGRAMME

3.1 The works programme is divided into two (2) phases: -
  1. Phase 1 (outside airport boundary)

    Involves the construction part of new exit taxiway, new elevated parking apron, hangarage facilities and other supporting buildings facilities that scheduled from 15/12/2021 until 14/06/2025.

  2. Phase 2 (within the airside/airport boundary)

    Involves the construction part of new exit taxiway, airside drainage, perimeter road, AGL and other associated works that scheduled from 13/06/2023 until 14/06/2025.