AIP Supplement for Malaysia

AIP SUP

05/2021

Effective from 08 APR 2021

to 28 MAY 2021

Published on 08 APR 2021

  KUALA LUMPUR FLIGHT INFORMATION REGION
KUALA LUMPUR INTERNATIONAL AIRPORT
KUALA LUMPUR / WMKK
EXTENSION OF PAVEMENT REHABILITATION WORKS ON RUNWAY 1 (14L/32R)
TAXIWAY A1 TO A11 AND ALL ASSOCIATED WORKS OF AIP SUP 13/2020

1  INTRODUCTION

1.1  Extension of pavement rehabilitation works on Runway 1 (14L/32R) and associated taxiway A1 to A11.

1.2  The working areas for the rehabilitation exercise is provided in APPENDIX A of this supplement.

2  PURPOSE

2.1  The purpose of this AIP Supplement is to notify the aviation industry of the schedule and the extend of the works areas due to construction activities on the aircraft movement areas, as well as the changes and restrictions on the movement areas.

3  SCOPE OF WORKS

3.1  The pavement rehabilitation works on the runway and taxiways comprise of the following scope of works:

  1. Reconstruction and resurfacing of existing asphaltic pavement layers (Taxiway A6 Only).

  2. Removal and reinstatement of affected Aeronautical Ground Lightings (AGL).

  3. Pavement markings.

  4. Pavement grooving on runway and portion of taxiways.

4  DURATION

4.1  The works are expected to be completed in 12 weeks.

5  WORK SECTION

5.1  Reconstruction and resurfacing of existing asphaltic pavement layers at Taxiway A6.

5.2  Asphaltic pavement grooving and marking works at areas on Runway from Ch. 0+241 to
Ch.3+782.

5.3  All distance for runway are taken from Runway 14L threshold and for Taxiways from Runway centerline.

See APPENDIX A

6  WORKS SCHEDULE AND WORKING HOURS

6.1  The tentative works schedule as follows:

SCHEDULEDURATIONWORKING HOURS
1 Mar 2021 to 28 May 202112 WeeksDaily 24 hours

6.2  Runway 14L/32R will be closed for operations and no reopening is allowed during construction stage in order to allow for 24 hours construction works.

7  MOVEMENT AREAS AND RESTRICTIONS

7.1  During construction stage, Runway 1 (14L/32R), Taxiway A and Taxiways A1 to A11 will be closed to all operations and all associated Aeronautical Ground Lights will be de-commissioned.

7.2  Visual aids denoting restricted use of areas on runway and taxiways shall be provided.

7.3  Precision approach lights and PAPI at both Runway 14L and 32R will be withdrawn.

7.4  ILS/GP at both Runway 14L and 32R will be withdrawn.

7.5  The declared distances for this work are as follows:

RWY
TORA
(M)
TODA
(M)
ASDA
(M)
LDA
(M)
RESA
(M)
14LNUNUNUNUNil
32RNUNUNUNUNil

7  SEE APPENDIX B for details.

8  REGULATIONS ON MOVEMENT AREAS

8.1  The routes to be used by aircraft when taxiing into and out of the apron will be specified by Air Traffic Control. The issuance by Air Traffic Control of a taxi route to an aircraft does not relieve the pilot-in-command of the responsibility to maintain separation with other aircraft on the movement area or to comply with Air Traffic Control directions intended to regulate aircraft movement.

9  PRECAUTIONS

9.1  During the construction period, pilots are advised to take note of the precautions on the presence of open excavation, workers, construction materials and construction equipment, particularly when taxiing adjacent to Runway, Taxiway and Apron while works within the cordoned/barricaded areas are in progress.

10  IMPLEMENTATION

10.1  This AIP Supplement and relevant charts will be applicable during the whole of the construction period.

11  CANCELLATION

11.1  This AIP Supplement will remain current until the works are completed.

CAPTAIN CHESTER VOO CHEE SOON

CHIEF EXECUTIVE OFFICER

CIVIL AVIATION AUTHORITY

MALAYSIA

Figure 1. APPENDIX A 05/2021
PDF../graphics/197081.pdf
Figure 2. APPENDIX B 05/2021
PDF../graphics/197082.pdf