AIP Supplement for Malaysia

AIP SUP

10/2020

Effective from 10 SEP 2020

to 02 FEB 2022

Published on 10 SEP 2020

  KOTA KINABALU FLIGHT INFORMATION REGION
LABUAN AIRPORT
CONSTRUCTION OF THE ROYAL MALAYSIAN AIR FORCE (RMAF) FACILITIES
AT LABUAN (RMAF) AIRBASE

1  INTRODUCTION

1.1  Reconstruction works of Taxiway B and resurfacing works of Taxiway A will be carried out at Labuan RMAF Airbase. Taxiway B had experienced settlement which resulted in its closure years ago. Reconstruction works will be carried out for the pavement. Taxiway A had experienced pavement cracking and resurfacing works will be carried out to repair the cracks.

2  OBJECTIVES

2.1  The purpose of this AIP Supplement is to notify the aviation industry of the reconstruction works on Taxiway B and resurfacing works on Taxiway A and its associated works.

3  WORK SECTIONS

3.1  The work will be carried out in two sections.

3.1.1  Section 1

This section involves the reconstruction works of Taxiway B which had commenced on 01 August 2020 and will complete by 31 March 2021. This section is flexible pavement.

3.1.2  Section 2

This section involves milling and resurfacing works of Taxiway A which shall commence on
01 April 2021 and will complete by 02 February 2022. This section is flexible pavement.

4  WORKS SCHEDULE

4.1  The works at the 2 sections will be carried out at differing times.

4.1.1  Section 1

4.1.1.1  Works in Section 1 starts from 01 August 2020 to 31 March 2021.

4.1.1.2  Taxiway B will be closed to all operation during the construction works, and their taxiway centerline and edge light will be de-energised.

4.1.1.3  Refer to APPENDIX A for details.

4.1.2  Section 2

4.1.2.1  Works in Section 2 will be carried out from 01 April 2021 to 02 February 2022.

4.1.2.2  Taxiway A will be closed to all operations during the resurfacing works, and their taxiway centerline and edge light will be de-energised. All aircraft’s operation will be operated on
Taxiway B.

4.1.2.3  Refer to APPENDIX A for details.

4.1.3  Schedule

4.1.3.1  The works schedule for Section 1 and Section 2 are as follows:

WORK DATESWORKING HOURS
Section 101 August 2020 to 31 March 2021Daily 1530 UTC to 2100 UTC except Sundays
Section 201 April 2021 to 02 February 2022Daily 1530 UTC to 2100 UTC except Sundays

4.1.3.2  During this phase of the works and within the times in the above table, the runway will not be closed to all operations. Works involving any portion of the Runway will be completed within the non-operating hours and operationally ready for flights the next day.

5  IMPLEMENTATION

5.1  This AIP Supplement will be applicable during the whole period of the construction works and is disseminated for immediate implementation. NOTAM will be issued regarding any subsequent changes to the works schedule.

6  CANCELLATION

6.1  This AIP Supplement will remain current until the construction works have been completed.

- END -